Emtract Ingest

Traffic Noise Protection Ordinance In force Unlisted

Overview

Jurisdiction
Germany
Topic
-
Instrument type
Regulation
Reference number
bimschv_16
Valid from
1990-06-21
Valid to
0808-01-01
Modified date
2021-03-01
Listed at
Unlisted draft
Withdrawn at
-
Description
Rules protecting neighbouring areas from traffic noise during the construction or substantial alteration of public roads, railway lines and tramways, including emission limit values and calculation methods.

Ask Question

Sources

Source URL Crawler Publish date
https://www.gesetze-im-internet.de/bimschv_16/xml.zip German Federal Law

Logs

Type Status Started at Finished at
No jobs yet.

Rule sets

Label Effective
Construction of public roads and rail routes 9999-01-01 — 9999-12-31
Conditions:
  • Activities contains No Linked Attribute Value “Bau von öffentlichen Straßen” “Bau von Schienenwegen der Eisenbahnen” “Bau von Schienenwegen der Straßenbahnen”
Substantial alteration through structural expansion 9999-01-01 — 9999-12-31
Conditions:
  • Activities contains No Linked Attribute Value “bauliche Erweiterung einer Straße um durchgehende Fahrstreifen” “bauliche Erweiterung eines Schienenwegs um durchgehende Gleise”
Substantial alteration involving a significant noise increase 9999-01-01 — 9999-12-31
Conditions:
  • Activities contains No Linked Attribute Value “erheblicher baulicher Eingriff mit Erhöhung um mindestens 3 Dezibel (A)” “erheblicher baulicher Eingriff mit Erhöhung auf mindestens 70 Dezibel (A) am Tage” “erheblicher baulicher Eingriff mit Erhöhung auf mindestens 60 Dezibel (A) in der Nacht”
Substantial alteration where the existing assessment level is already high 9999-01-01 — 9999-12-31
Conditions:
  • Activities contains No Linked Attribute Value “erheblicher baulicher Eingriff mit Erhöhung eines bestehenden Pegels von mindestens 70 Dezibel (A) am Tage” “erheblicher baulicher Eingriff mit Erhöhung eines bestehenden Pegels von mindestens 60 Dezibel (A) in der Nacht”

Questions this regulation asks

Attributes only this regulation asks about — criteria no general attribute expresses. A company answers each once.

This regulation asks no questions of its own — every condition uses a general attribute.

Obligations

Title Kind Rule set
Compliance with immission limit values Other -
Description:
For construction or substantial alteration, ensure that the assessment level does not exceed the applicable daytime and nighttime immission limit values.
Frequency:
Event-triggered
Check frequency:
Event-triggered
Products/Services:
Public roads and rail routes of railways and tramways whose construction or substantial alteration requires assessment of traffic noise.
Checking responsibility:
-
Check method:
Checking the assessment level against the immission limit values specified in § 2(1).
Rule set:
-
Source reference:
§ 2 Abs. 1
Source excerpt:
ist bei dem Bau oder der wesentlichen Änderung sicherzustellen, daß der Beurteilungspegel einen der folgenden Immissionsgrenzwerte nicht überschreitet:
Report on implementation of the Ordinance Reporting -
Description:
The Federal Government must report to the German Bundestag by 2025 at the latest and subsequently every ten years on implementation of the Ordinance, including whether the immission limits reflect the state of noise-effects research and whether further measures are required.
Frequency:
Biennial
Check frequency:
Other
Products/Services:
Implementation of the Ordinance and the immission limit values specified in § 2(1).
Checking responsibility:
Federal Government
Check method:
Preparation and submission of a report to the German Bundestag.
Rule set:
-
Source reference:
§ 2 Abs. 4
Source excerpt:
Die Bundesregierung erstattet spätestens im Jahre 2025 und dann fortlaufend alle zehn Jahre dem Deutschen Bundestag Bericht über die Durchführung der Verordnung.
Calculation of assessment levels for roads Due Diligence -
Description:
Calculate the assessment level for roads under Section 3 in conjunction with Section 1 of RLS-19, separately for the daytime and nighttime assessment periods.
Frequency:
Event-triggered
Check frequency:
Event-triggered
Products/Services:
Assessment levels for roads.
Checking responsibility:
-
Check method:
Calculation under Section 3 in conjunction with Section 1 of RLS-19, separately for daytime and nighttime.
Rule set:
-
Source reference:
§ 3 Abs. 1
Source excerpt:
Der Beurteilungspegel für Straßen ist nach Abschnitt 3 in Verbindung mit Abschnitt 1 der Richtlinien für den Lärmschutz an Straßen – Ausgabe 2019 – RLS-19 (VkBl. 2019, Heft 20, lfd. Nr. 139, S. 698) zu berechnen. Die Berechnung hat getrennt für den Beurteilungszeitraum Tag (6 Uhr bis 22 Uhr) und den Beurteilungszeitraum Nacht (22 Uhr bis 6 Uhr) zu erfolgen.
Calculation of assessment levels for rail routes Due Diligence -
Description:
Calculate the assessment level for rail routes under Annex 2, separately for the daytime and nighttime assessment periods.
Frequency:
Event-triggered
Check frequency:
Event-triggered
Products/Services:
Assessment levels for rail routes.
Checking responsibility:
-
Check method:
Calculation under Annex 2, separately for daytime and nighttime.
Rule set:
-
Source reference:
§ 4 Abs. 1
Source excerpt:
Der Beurteilungspegel für Schienenwege ist nach Anlage 2 zu berechnen. Die Berechnung hat getrennt für den Beurteilungszeitraum Tag (6 Uhr bis 22 Uhr) und den Beurteilungszeitraum Nacht (22 Uhr bis 6 Uhr) zu erfolgen.
Determination of acoustic parameters Approval -
Description:
Divergent rail technology or noise-control innovations may be taken into account in calculations only if the competent authority has previously determined acoustic parameters.
Frequency:
Event-triggered
Check frequency:
Event-triggered
Products/Services:
Divergent rail technology and noise-control innovations.
Checking responsibility:
Federal Railway Authority for federal railways; the authority responsible under Land law for other railways.
Check method:
Application procedure with the information and documents specified in § 5(4).
Rule set:
-
Source reference:
§ 5 Abs. 1 Satz 1
Source excerpt:
Abweichende Bahntechnik oder schalltechnische Innovationen dürfen bei der Berechnung des Beurteilungspegels nach § 4 Absatz 1 Satz 1 nur berücksichtigt werden, wenn die zuständige Behörde in einem Verfahren nach Maßgabe der Absätze 2 bis 4 für die Berechnung akustische Kennwerte festgelegt hat.
Information and documents required in the application Reporting -
Description:
The application must contain a description of the technology or innovation, an expert report by a recognized measuring body, a proposed allocation to a rule with a data sheet, and a description of changes in acoustic effectiveness caused by customary operational wear.
Frequency:
Event-triggered
Check frequency:
Event-triggered
Products/Services:
Applications for determination of acoustic parameters for divergent rail technology or noise-control innovations.
Checking responsibility:
Competent authority under § 5(2), first sentence.
Check method:
Review of the description, expert report, allocation proposal with data sheet, and description of changes caused by wear.
Rule set:
-
Source reference:
§ 5 Abs. 4
Source excerpt:
Der Antrag nach Absatz 2 Satz 1 muss folgende Angaben und Unterlagen enthalten:
Standards-compliant calculation software Due Diligence -
Description:
Software products used for the calculation must ensure a standards-compliant representation of this provision.
Frequency:
Event-triggered
Check frequency:
Event-triggered
Products/Services:
Software products used to calculate sound immissions from rail routes.
Checking responsibility:
-
Check method:
Checking whether the software products used represent this provision in conformity with the applicable standard.
Rule set:
-
Source reference:
Anlage 2 Nr. 1
Source excerpt:
Die für die Berechnung verwendeten Softwareprodukte müssen die normgerechte Abbildung dieser Vorschrift sicherstellen;
Performance of verification measurements Due Diligence -
Description:
The applicant must have the verification measurements under Numbers 9.1.1 to 9.1.7 carried out by a recognized measuring body.
Frequency:
Event-triggered
Check frequency:
Event-triggered
Products/Services:
Evidence and measurements for divergent rail technology and noise-control innovations.
Checking responsibility:
Applicant; recognized measuring body.
Check method:
Performance of verification measurements by a recognized measuring body.
Rule set:
-
Source reference:
Anlage 2 Nr. 9.1.8
Source excerpt:
Der Antragsteller hat die Nachweismessungen nach den Nummern 9.1.1 bis 9.1.7 durch eine anerkannte Messstelle durchführen zu lassen.
Expert report by the recognized measuring body Reporting -
Description:
The commissioned recognized measuring body must prepare an expert report on the measurements conducted, containing the prescribed information and documents.
Frequency:
Event-triggered
Check frequency:
Event-triggered
Products/Services:
Expert report on measurements conducted under Numbers 9.1.1 to 9.1.7.
Checking responsibility:
Recognized measuring body commissioned by the applicant.
Check method:
Preparation of an expert report containing the information and documents listed in Annex 2, Number 9.3(a) to (g).
Rule set:
-
Source reference:
Anlage 2 Nr. 9.3
Source excerpt:
Die vom Antragsteller beauftragte anerkannte Messstelle nach Nummer 9.1.8 erstellt über die nach Maßgabe der Nummern 9.1.1 bis 9.1.7 durchgeführten Messungen ein Gutachten, das die folgenden Angaben und Unterlagen enthalten muss:

Measures

No measures.

Penalties

No penalties.

Milestones

Date Type Description
2014-12-31 Other Cut-off date for already opened and publicly announced plan-approval procedures for rail-route projects.
Source reference:
§ 4 Abs. 3
Source excerpt:
für die bis zum 31. Dezember 2014 das Planfeststellungsverfahren bereits eröffnet und die Auslegung des Plans öffentlich bekannt gemacht worden ist
2021-02-28 Other End of the period during which the previous version applies to certain road-construction projects.
Source reference:
§ 6
Source excerpt:
in der bis zum Ablauf des 28. Februar 2021 geltenden Fassung
2021-03-01 Other Cut-off date for the transitional rule on calculating the assessment level for road-construction projects.
Source reference:
§ 6
Source excerpt:
wenn vor dem Ablauf des 1. März 2021
2025-12-31 Other Latest date for the Federal Government's first report to the German Bundestag on implementation of the Ordinance.
Source reference:
§ 2 Abs. 4
Source excerpt:
Die Bundesregierung erstattet spätestens im Jahre 2025

Linked regulations

No linked regulations.