Environmental Impact Assessment Directive In force Unlisted

Overview

Jurisdiction
European Union
Topic
-
Instrument type
Directive
Reference number
2011/92/EU
Valid from
2012-02-17
Valid to
2026-08-06
Modified date
2011-12-13
Listed at
Unlisted draft
Withdrawn at
-
Description
Establishes environmental impact assessment requirements for public and private projects likely to have significant effects on the environment, including obligations for developers, authorities and public participation.

Ask Question

No regulation sources to answer questions from yet.

Sources

No regulation sources yet.

Rule sets

Label Effective
Annex I projects 2012-02-17 — 9999-12-31
Applies from milestone:
Entry into Force (2012-02-17)
Expires at milestone:
-
Conditions:
  • Activities contains No Linked Attribute Value “crude-oil refineries” “thermal power stations or other combustion installations with a heat output of 300 megawatts or more” “nuclear power stations or other nuclear reactors” “integrated works for the initial smelting of cast iron and steel” “integrated chemical installations” “major railway, airport, motorway, port or road construction projects” “hazardous-waste disposal installations” “large groundwater abstraction or recharge schemes” “large water-transfer works” “large waste-water treatment plants” “commercial petroleum or natural-gas extraction” “large dams or water-storage installations” “large pipelines” “intensive poultry or pig rearing installations” “large pulp, paper or board plants” “large quarries or open-cast mines” “large overhead electrical power lines” “large petroleum, petrochemical or chemical storage installations” “carbon-dioxide storage or capture installations” “Annex I project changes or extensions meeting the applicable thresholds”
Annex II projects determined to require assessment 2012-02-17 — 9999-12-31
Applies from milestone:
Entry into Force (2012-02-17)
Expires at milestone:
-
Conditions:
  • Activities contains No Linked Attribute Value “Annex II agriculture, forestry or aquaculture projects” “Annex II extractive-industry projects” “Annex II energy-industry projects” “Annex II metal, mineral, chemical, food, textile, leather, wood, paper or rubber industry projects” “Annex II infrastructure projects” “Annex II waste-disposal or waste-water projects” “Annex II tourism and leisure projects” “Annex II project changes or extensions with potentially significant adverse environmental effects”

Questions this regulation asks

Attributes only this regulation asks about — criteria no general attribute expresses. A company answers each once.

This regulation asks no questions of its own — every condition uses a general attribute.

Obligations

Title Kind Rule set
Provide project description Reporting -
Description:
The developer must provide a description of the project, including its site, design, size, physical characteristics, land-use requirements, production processes, and expected residues and emissions.
Frequency:
One-time
Check frequency:
-
Products/Services:
Projects under Article 4 that are subject to an environmental impact assessment
Checking responsibility:
Competent authority
Check method:
Review of the project information supplied by the company during the consent and environmental impact assessment procedure
Rule set:
-
Source reference:
Article 5(3)(a)
Source excerpt:
The information to be provided by the developer in accordance with paragraph 1 shall include at least: (a) a description of the project comprising information on the site, design and size of the project;
Outline project alternatives Reporting -
Description:
The developer must outline the main project alternatives studied and indicate the main reasons for the choice, taking environmental effects into account.
Frequency:
One-time
Check frequency:
-
Products/Services:
Projects under Article 4 that are subject to an environmental impact assessment
Checking responsibility:
Competent authority
Check method:
Review of the alternatives and reasons for the choice presented in the environmental assessment information
Rule set:
-
Source reference:
Article 5(3)(d)
Source excerpt:
an outline of the main alternatives studied by the developer and an indication of the main reasons for his choice, taking into account the environmental effects;
Identify and assess environmental effects Due Diligence -
Description:
The developer must provide the data required to identify and assess the main effects of the project on the environment, including its likely significant effects.
Frequency:
One-time
Check frequency:
-
Products/Services:
Projects under Article 4 that are subject to an environmental impact assessment
Checking responsibility:
Competent authority
Check method:
Review of the collected data and description of the likely significant environmental effects
Rule set:
-
Source reference:
Article 5(3)(c)
Source excerpt:
the data required to identify and assess the main effects which the project is likely to have on the environment;
Describe forecasting methods Due Diligence -
Description:
The developer must describe the forecasting methods used to assess the environmental effects.
Frequency:
One-time
Check frequency:
-
Products/Services:
Projects under Article 4 that are subject to an environmental impact assessment
Checking responsibility:
Competent authority
Check method:
Review of the forecasting methods used and the assessment of effects
Rule set:
-
Source reference:
Annex IV, point 5
Source excerpt:
The description by the developer of the forecasting methods used to assess the effects on the environment referred to in point 4.
Describe mitigation measures Due Diligence -
Description:
The developer must describe the measures envisaged to prevent, reduce and, where possible, offset significant adverse environmental effects.
Frequency:
One-time
Check frequency:
-
Products/Services:
Projects under Article 4 that are subject to an environmental impact assessment
Checking responsibility:
Competent authority
Check method:
Review of the measures envisaged to prevent, reduce and, where possible, offset significant adverse effects
Rule set:
-
Source reference:
Annex IV, point 6
Source excerpt:
A description of the measures envisaged to prevent, reduce and where possible offset any significant adverse effects on the environment.
Provide non-technical summary Reporting -
Description:
The developer must provide a non-technical summary of the environmental assessment information.
Frequency:
One-time
Check frequency:
-
Products/Services:
Projects under Article 4 that are subject to an environmental impact assessment
Checking responsibility:
Competent authority
Check method:
Review of the non-technical summary of the environmental assessment information
Rule set:
-
Source reference:
Article 5(3)(e)
Source excerpt:
a non-technical summary of the information referred to in points (a) to (d).
Indicate difficulties in compiling information Reporting -
Description:
The developer must indicate any difficulties encountered when compiling the required information, including technical deficiencies or lack of know-how.
Frequency:
One-time
Check frequency:
-
Products/Services:
Projects under Article 4 that are subject to an environmental impact assessment
Checking responsibility:
Competent authority
Check method:
Review of the information on technical deficiencies or lack of know-how encountered when compiling the required information
Rule set:
-
Source reference:
Annex IV, point 8
Source excerpt:
An indication of any difficulties (technical deficiencies or lack of know-how) encountered by the developer in compiling the required information.

Measures

No measures.

Penalties

No penalties.

Milestones

Date Type Description
2011-12-13 Adopted Adoption of Directive 2011/92/EU
Source reference:
Directive title
Source excerpt:
of 13 December 2011
2012-02-17 Entry into Force Entry into force of the Directive on the 20th day following its publication in the Official Journal
Source reference:
Article 15
Source excerpt:
This Directive shall enter into force on the 20th day following its publication in the Official Journal of the European Union.

Linked regulations

Type Regulation
Repeals Directive 85/337/EEC
Cites Council Directive 85/337/EEC
Cites Directive 2008/1/EC
Cites Directive 2003/4/EC
Cites Directive 2008/98/EC
Cites Council Directive 91/271/EEC
Cites Directive 2009/31/EC
Cites Directive 2009/31/EC
Cites Directive 2009/31/EC
Cites Directive 2009/147/EC and Council Directive 92/43/EEC
Cites Council Directive 97/11/EC
Cites Directive 2003/35/EC
Cites Directive 2009/31/EC